-
11/18: Pottawatomie Habitat Partnership House #9 is almost
complete. Watch for house blessing information in a future
update.
-
11/4: We will be finishing the cabinet installation, painting
and trim work and finishing other miscellaneous items on
November 3rd and 10th. The house is close to completion.
-
10/21: We will be finishing the cabinet installation,
painting and trim work on October 27th. Miscellaneous
electrical work will also be done. Volunteers are always
needed. Work hours are from 8:30 – til mid afternoon on
Saturdays.
-
9/30: We will continue work on cabinets, trim and electrical
on October 6th , 13th and 20th. We will also be painting on
these dates.
-
9/23: We will start cabinets and trim on September 29th and
October 6th and will also be painting. Volunteers are always
needed. Work hours are from 8:30 – until mid afternoon on
Saturdays.
-
9/2: The build schedule has changed somewhat. We will be
priming and painting on the 15th. No volunteers will be
needed on the 22nd. We will start the cabinets and trim on
September 29th and October 6th.
-
8/26: We will be finishing the drywall and start priming on
September 8th. Flooring will be done on the 15th and 22nd.
Cabinets and trim will be started at the end of September and
continue into October.
-
8/19: Drywall should begin this week and if complete, we will
start priming and painting on the 25th. We will start trim
work at the end of August.
-
8/12: We will continue doing insulation, electrical work and
other miscellaneous items on the 18th. Drywall should begin
the week of August 20th. Priming and painting will begin at
the end of August.
-
8/5: On Saturday August 11th, we will be doing insulation,
electrical work and other miscellaneous items. Drywall is
scheduled to begin the week of August 20th.
-
7/29: Electrical work and siding have started and will
continue on August 4th. We will also start the insulation.
-
7/22: On Saturday, July 28th we will be doing electrical
work, finishing the siding, and possibly starting insulation.
-
7/8: On Saturday, July 14th we will be doing shingling and
setting the doors and windows. We will also be doing some
electrical work.
-
7/1: We will NOT be working on Saturday, July 7th. We will be
working on July 14th and will be finishing the shingles and
windows and doors and also will be doing electrical work. We
are behind in the schedule due to the rain on June 23rd.
-
6/24: On Saturday, June 30th, we will finish roof framing,
start working on shingles and begin to set windows and doors.
-
6/17: We will continue with the roof framing on Sat. June
24th and also start shingling if possible. We will be setting
the windows and doors the following weekend.
-
6/10: We are still working on the framing and roof framing.
We will continue with the roof framing on Sat. June 16th and
start shingling on the 23rd.
-
5/29: We hope to complete roof framing on
Saturday, June 9 and start shingling on Saturday, June 16. We
need volunteers. If you are at least 16, can pound a nail,
and enjoy a free lunch, you’re qualified. Work starts at
8:00. If you are coming, please bring a hammer.
-
5/21: Due to the holiday weekend, we will not
work next Saturday, the 26th. We hope to complete framing and
start roofing on Saturday, June 2nd.r.
-
Framing will continue and hopefully be
finished next Saturday, May 19th.
-
4/27: Foundation construction is proceeding as
planned, therefore we still expect that lunch and
construction volunteers will be needed starting next
Saturday, May 5th for decking, and if time permits, framing.
-
4/18: The footers and foundation walls for
House 9 were poured last week so our current expectation is
that lunch and construction volunteers will be needed
starting Saturday, May 5th. This date is subject to change,
so monitor future updates for specifics.
-
Work on house number 9, located at the corner
of Maple and Kane Avenues in Valley View, has started. The
well is in and the excavation/foundation work is currently in
progress. Completion of this work is very much governed by
the weather but the current expectation is volunteers for
construction and lunches will be needed in early May.
-
The Automotive Division of Robert Bosch Corp
wants to help us build a house! They will commit $30,000,
they would like to work approximately 15 days, and will
provide lunch for all on the days they work.